The first step in encouraging BIM is to engage BIM capable professionals, to include BIM capabilities in bid requirements.

By that I don’t mean a description of what BIM processes a bidder must undertake, but a request the bidders provide a description of the BIM processes they already do. In this early period of BIM take up you may extend this to include BIM processes bidders intend or are prepared to implement.

The aim is to get them to make an offer, for the use of BIM to be their responsibility.

But keep in mind BIM is but one aspect of why you select a particular bidder. Professionals are primarily engaged for their capabilities in their area of expertise, and service performance. BIM is only a tool, it won’t compensate for lack of expertise or poor service.


The second step is to ensure agreements and contractual arrangements allow BIM processes to work freely. As mentioned above all BIM processes (except facilities management) are between the design and construction teams.  This is a challenge for those drawing up and approving agreements. Traditionally contracts have been designed to be between the person paying and the one doing the work. BIM capable agreements require additional clauses that set out how those being paid will interact with third parties – other project participants.

Obviously there are a whole raft of issues to consider, and the type of BIM processes undertaken will influence what specific requirements will be. Which is another complication. The owner is not a participant in these BIM processes (with the exception of facilities management), nor are the exact BIM processes known at the beginning of a project before everyone is signed up.

The BIM evangelist’s answer is to ignore reality and assume the owner HAS to be a BIM participant, and that everyone HAS to be signed up at the very beginning of a project (as evidenced by the push for Integrated Project Delivery type contracts).

But it doesn’t have to be this way. Contracts need do no more than ensure the free flow of information in BIM type format. That is, BIM information created by project participants must be freely available to all other project participants. Sounds simple but there is a paranoia about theft of intellectual property throughout the industry. The default position is to withhold information. Contracts need to specifically override this position.

Tied in with this is that all information in deliverables must match. That information on drawings and schedules match information in BIM models. And that recipients of BIM models can rely on the information in those models. It must also be specified this only applies to information a participant would ordinarily provide. If an architect includes some ducts in their model for context, that doesn’t make them responsible for the completeness and accuracy of those ducts.

Contracts could be further extended to be BIM friendly. For example allowing for project participants to do modelling for others participants, whilst responsibility is retained by the requesting party. So the architects might model ductwork for the mechanical engineers (or sub-contractor) but the engineers or sub-contractor must check and approve that modelling work.

BIM capable agreements and contracts are in their infancy and no one can predict what their eventual form will be. But I believe if we approach them with a view to encouraging, or allowing BIM, rather than enforcing BIM, we will end up with much more useful agreements and therefore BIM workflows.


Rather than demanding direct BIM deliverables they will never use owners should look at requesting evidence of BIM. Requesting evidence also means that even if specific BIM is not defined by owners they can still influence the use of it on their project.

There is nothing wrong with requesting evidence of BIM processes as deliverables. The owner may not participate in the creation of a BIM Management Plan, but they can include it as a deliverable. They may not attend clash coordination meetings but minutes of outcomes can be requested.

However evidence of BIM should never be provided for ‘approval’. Not only does this pass some responsibility back on to the approver (the owner) but has the potential to hold up the project.

The purpose is purely to ensure what has been promised (see SELECTION section above) is being done. An owner may reject a BIM Management Plan as being incomplete or inadequate, but should never ‘approve’ it.


BIM is often touted as ‘costing more’. But research has shown overall a project using BIM processes is more cost efficient. It may be directly cheaper and/or quicker to build, or a more complex result is achievable for the same time and money.

The problem is that not all participants share these cost savings equally. Which is easy to see when you look at how BIM works. BIM models are created early in a project and passed on to participants through the term of the project. The architect models the building, the mechanical engineer uses that model to do energy calculations, the mechanical engineer’s model is passed on to the mechanical sub-contractor who uses it as a basis for shop drawing and CAM, this model is passed to the facilities manager to populate their energy management system. The further up the chain the more complete the model is and greater the savings in time and effort. And of course the owner is at the top of this chain.

Another issue is some participants are required to do more than they have previously done. Engineers traditionally produce diagrammatic drawings and performance requirements for equipment. With BIM they have to model their work accurately and select specific components (otherwise you can’t model them). Of course paying them extra to do this work is not the only solution. But someone has to do it, and no one is going to do it for free.

BIM also requires more work up front. The mechanical engineer can’t do an energy analysis on a half modelled building. If the point of BIM is to create a complete virtual building to test its buildability then it has to be completely designed and modelled before construction starts.

BIM may ‘cost more’ for some, but overall it does not. So it is not necessarily about spending more (although that will certainly bolster use of BIM!). To encourage BIM there needs to be a re-think of where and when money is spent. More money is required at the pre-construction BIM model creation stage.

This may be in the form of extra for design professionals, the appointment of additional professionals, or bringing forward engagements (e.g. services sub-contractors).

And within those engagements payment schedules need to be revised. Fees are normally broken up into stages. With BIM more work is done – more hours expended – in early stages than traditional work methods.

I don’t believe a similar concession is required at construction as BIM processes bring enormous cost benefits to contractors. In fact I believe owners need to be careful they are not paying for BIM efficiencies that the contractor will pocket. Any BIM from the design team should be treated as an asset that benefits the contractor.


And of course owners can directly encourage use of BIM. Not by demanding it, but by having a strong expectation that the team will use BIM processes. Owners don’t need to have intimate knowledge of those processes, but they can expect their design and construction professionals do.


So what is the answer, should owners ask for BIM?

As is the case with most questions, that depends. But here are some recommendations.

Ignore BIM

Not recommended. If you don’t understand BIM or don’t want it don’t stand in the way of those that do. The fact others use it will not cost you more, nor will it increase your workload.

Allow BIM

If you are unsure and don’t really understand much about BIM this is a valid approach. It provides an opportunity to learn from others.

Encourage BIM

Encouraging BIM is the best approach if the owner does not have a BIM based FM system. It allows the design and construction team to make best use of BIM for their purposes. It also creates a wealth of BIM data. It is not structured for FM use, but can still be mined for useful FM data.

Participate in BIM

A truly BIM project has everyone participating in BIM, including the owner. Owners can participate by having their own properly set up FM system that uses BIM.

Having skin in the game, so to speak, means BIM deliverables can be properly valued as to their worth. And if everyone is a participant BIM planning can be undertaken with confidence, and result in even greater benefits than individual use of BIM brings.

Demand BIM

Not recommended. Unless you are a conglomerate with architects, engineers and contractors all under the same roof you should not be dictating what BIM is done. Even then care must be taken to ensure some participants are not working inefficiently for questionable benefits elsewhere. Copied from blogger.com